This article has background about the project and the schedule of weeklong public hearings (that began on January 5) and some topics to consider while making your voice heard. Also,a comprehensive,printable document(pdf)from the MN PUC about this process can be found here. There are several ways to be part of these public hearings for "the Matter of the Application of North Dakota Pipeline Company LLC for a Certificate of Need for the Sandpiper Pipeline Project in Minnesota."

Project Description

North Dakota Pipeline Company LLC (NDPC) proposes to build a crude oil pipeline:

 

  • Approximately 616 miles long, from Tioga, North Dakota to Superior, Wisconsin
  • Approximately 302 miles of the new pipeline would be located in Minnesota
  • With a 24 inch diameter and a 225,000 barrels per day (bpd) capacity from North Dakota to Clearbrook, Minnesota
  • With a 30 inch diameter and a 375,000 barrels per day (bpd) capacity from Clearbrook, Minnesota to Superior, Wisconsin
  • With approximately 25 to 50 feet of new right-of-way and 40 to 70 feet of temporary right of-way

The proposed project includes a new terminal facility near the existing terminal in Clearbrook, Minnesota.

The proposed project would be located in Aitkin, Carlton, Cass, Clearwater, Crow Wing, Hubbard, Polk, Red Lake, and Wadena counties. 

Topics to consider:

  • Sandpiper will help alleviate rail and highway congestion by transporting increased oil supplies via pipelines.
  • Sandpiper will create 1,500 good-paying jobs and spur economic investment in Minnesota.
  • Sandpiper will increase our nation's energy independence and improve our energy security.

Sandpiper will increase property tax revenue in every county it crosses, adding tax revenue for rural counties that do not have strong business-tax bases.

Public hearing information

Monday, January 5, 2015

2:00 p.m.

Saint Paul RiverCentre 

Ballrooms A and B

175 West Kellogg Boulevard

St. Paul MN 55102

RiverCentre Information

 

Tuesday, January 6, 2015

2:00 p.m.

Downtown Holiday Inn 

Ballroom

200 West 1st Street

Duluth MN 55802

Parking is free for public hearing guests

Wednesday, January 7, 2015

2:00 p.m.

Bemidji State University

Hobson Union - Ballroom

1500 Birchmont Drive Northeast

Bemidji MN 56601

University Campus Map

Thursday, January 8, 2015

2:00 p.m.

Crookston Inn & Convention Center

Ballrooms 1 and 2

2200 University Avenue

Crookston MN 56716

Crookston Inn Information

Friday, January 9, 2015

2:00 p.m.

St. Cloud River's Edge Convention Center

Herberger Suite

10 4th Avenue South

St. Cloud MN 56301

Convention Center Information

If you wish to speak:

  • Please arrive 15 minutes early (at 1:45 p.m.) to get your name on the MPUC list.

Inclement weather:

Public comments:

 The MPUC's public comment period for Sandpiper will remain open through January 23, 2015, at 4:30 p.m. (comments must be received by 4:30 p.m. and will not be accepted if received after that time).

To submit written comments:

  • Visit www.mn.gov/puc, select "Comment on an Issue," and go to docket 13-473 to add your comments; or
  • Mail comments to Minnesota Public Utilities Commission (reference docket 13-473) , 121 - 7th Place East, Suite 350, St. Paul, MN 55101.

Again, topics to consider:

  • Sandpiper will help alleviate rail and highway congestion by transporting increased oil supplies via pipelines.
  • Sandpiper will create 1,500 good-paying jobs and spur economic investment in Minnesota.
  • Sandpiper will increase our nation's energy independence and improve our energy security.

Sandpiper will increase property tax revenue in every county it crosses, adding tax revenue for rural counties that do not have strong business-tax bases.

For more information:

Jason George
jason.george@nrg-llc.com
(612) 215-6096 Direct 
(612) 791-2585 Cell 
(612) 347-6780 Fax